Is there any way to restrict time entry into PWA by date? I don't want
anyone to be able to be enter time in PWA after 10/1/07 for any dates prior
to then.

Thanks,
Jennifer
 
D

Dale Howard [MVP]

Jennifer --

In the future, please tell us what version of Project Server you are using.
2002, 2003, or 2007? If you are using 2003, you can use the Managed Time
Periods functionality to close past time periods and future time periods,
and restrict time entry only to current time periods, as defined by the
Project Server administrator. If you are using 2007, the Project Server
administrator can also close past and future time periods as well. Hope
this helps.
 