Restricting timesheet day entry

J

John

In the time sheet I have many task that end at deferent dates
I need a way to prevent the resource from booking time after the end date for that task
Eg.
- Task1 2 days Sun,Mo
- Task2 2 days Mon,Tu
John is assigned on both, On Tuesday john can only enter time for task2 not task1
 
D

Dale Howard [MVP]

John --

Microsoft Project Server does not have the capabilities that you believe you
need. The closest that the software can come to your requirements is the
use of managed time periods in Project Server 2003, but I don't believe that
even that feature would satisfy your requirements. Instead, I would
recommend that you make this a training and performance issue, and that your
project managers enforce this policy on the entry of actuals. Hope this
helps.
 