R
RTucker
I have a situation where the wrong Resource Rate was used, but not discovered
until halfway through the project completion. We are running EVM. We will
apply a credit to the client's account for the overcharge.
What is the best way to address this situation? Do we change the rate to
retroactivate the BCWP? Being halfway through the project, how do we
re-baseline?
I thought about adding a negative fixed cost equal to the credit at the top
of the project (timephased to the date the credit will be issued, and
changing the resource's rate moving forward, but not sure that this is the
correct approach.
Ideas?
until halfway through the project completion. We are running EVM. We will
apply a credit to the client's account for the overcharge.
What is the best way to address this situation? Do we change the rate to
retroactivate the BCWP? Being halfway through the project, how do we
re-baseline?
I thought about adding a negative fixed cost equal to the credit at the top
of the project (timephased to the date the credit will be issued, and
changing the resource's rate moving forward, but not sure that this is the
correct approach.
Ideas?