Risk and task in WSS

C

Chamutal

I have couple of questions about linking a task to risk as trigger or as affected task :
1. Can I see in Project Proffesional an indicator that the task is linked to a risk ?
2. Do I get any kind of message when the task starts \ completed \ late ... ?
 
D

Dale Howard [MVP]

Chamutal --

1. You can see the risk indicator in the Indicators column of any Project
Center view in PWA, and in a detailed Project view for the project in PWA.
You cannot see the risk indicator in the project plan in Microsoft Project
Professional.

2. You can set up a subscription for reminders about overdue tasks for your
team members through PWA, however, you cannot set up a subscription for
reminders on one specific task. Project Server will send you an e-mail when
a team member's task is overdue.

Hope this helps.




Chamutal said:
I have couple of questions about linking a task to risk as trigger or as affected task :
1. Can I see in Project Proffesional an indicator that the task is linked to a risk ?
2. Do I get any kind of message when the task starts \ completed \ late
.... ?
 
Top