Risks & Issues

R

RandyK

Is there a way that we can report on risks and issues accross the enterprise
(all projects) in MSPS (2003)?

For example, we have 250 active projects and we want to report on all high
prioirty issues accross all projects - or perhaps a report that lists all
risks accross all projects with probability of occurence greater than 60%.
Are these types of reports possible in MSPS? If so, how? (or do we need to
mine the data using a third party system?)
 
D

Dale Howard [MVP]

RandyK --

You need to use a reporting tool such as Crystal Reports or SQL Reporting
Services. Hope this helps.
 