T
Trent Helms
Assuming a matrix environment we have Project Managers and Resource
Managers how would the assignment of tasks be handled?
1) Does the Resource Manager actually set the start and end dates of
assignments or do they only supply the resource giving the PM the
responsibility?
2) When assigning resources for particular dates is it okay to use
constraints? For example a resource works on 5 different projects.
Should the resource manager or project manager assign hard dates so
that the resource knows specifically what to work on? For planning I
understand the use of leveling would be the first route. But
operationally when the team is making adjustments daily of total team
tasks should they just go in and modify the dates?
Thanks in advance,
Trent Helms
[email protected]
Managers how would the assignment of tasks be handled?
1) Does the Resource Manager actually set the start and end dates of
assignments or do they only supply the resource giving the PM the
responsibility?
2) When assigning resources for particular dates is it okay to use
constraints? For example a resource works on 5 different projects.
Should the resource manager or project manager assign hard dates so
that the resource knows specifically what to work on? For planning I
understand the use of leveling would be the first route. But
operationally when the team is making adjustments daily of total team
tasks should they just go in and modify the dates?
Thanks in advance,
Trent Helms
[email protected]