Roll up fixed costs into summary tasks

D

Dennis Vlasich

When looking at summary tasks that show both Fixed Cost as well as 'Cost'
(labor) fields, only the Total Cost rolls up into the summary tasks. It's
very confusing to look at a summary task with a Fixed Cost column that does
not contain the sum of the fixed cost amounts but then adds it into the Total
Cost column. Who's bright idea was this?
--
Dennis Vlasich
Claremont, CA

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...bc3e-4884e182ac83&dg=microsoft.public.project
 
M

Mike Glen

Hi Dennis,

Welcome to this Microsoft Project newsgroup :)

The Microsoft Project Developers :) However, there may be some requirement
to enter a fixed cost in a summary to cover the summary's costs: eg
consultant's fee, cost of blueprints, purchase of equipment, etc. So there
is some sense in it :)

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top