Roll up of baseline costs

U

Ursula

Has anyone experienced (or does anyone know why) the roll up to summary of
individually baselined tasks does not always add correctly?

Example: A task (1.1.7.1) baselined in the past at $136,654.66. A new task
(1.1.7.2) is added and individually baselined at $195,006.15 (with "roll up
baseline to all summary tasks" selected.) The summary baseline costs for
1.1.7 shows as $262,440.45.

I believe $136,654.66 + $195,006.15 = $331,660.81.
 