Rolled up milestones

M

Marc Daoust

Hi
I am looking at a way to roll up all milestone on to one bar. Does anyone know if this is possible and if yes, how would I go about it

Thanks
Marc
 
J

J Baird

Display this in the web or in MSP Professional?

In MSP Professional:
Milestones (and tasks) will only rollup to parent level (and above) summary
tasks. Set the milestone task's Rollup field to Yes for each milestone
task, and set Rollup to No for each non-milestone task. Rollu pshould be
set to Yes for the summary tasks where you want the milestones displayed.

You may also need to edit the Bar Styles:
1) Select [Format][Bar Styles]
2) See if there's a Rolled Up Milestone bar near the bottom of the Bar Style
list (if it's at the top of the list, the symbol is probably being written
over by the summary bar). If there isn't one, you can add it to the bottom
of the list.
a) The Rolled Up Milestone bar often has the following settings:
Appearance: shape=diamond : type=framed : color=black
Show For: Milestone,Rolled Up,Not Summary
Row: 1
From: Start
To: Start

Marc Daoust said:
Hi,
I am looking at a way to roll up all milestone on to one bar. Does anyone
know if this is possible and if yes, how would I go about it?
 
M

Marc Daoust

Thank you for the answer, I should have been more specific..... I was looking for help on creating this type of report in both Pro and web.

Marc
 
Top