Rolled-up Status Reports

C

Cecile

Is there a way for the PM to merge all requested weekly status reports
submitted by his team members?
Thanks.
 
D

Dale Howard [MVP]

Cecile --

All status reports responses are merged automatically during each reporting
period in the Team Status Report at the top of the list of reponses on the
View Status Report Responses... page. Hope this helps.
 
D

Dale Howard [MVP]

Cecile --

If you have created multiple Status Report requests, then you will have
multiple Team Status Reports. What I would recommend is that you do the
following:

1. Display the responses for the first Status Report request
2. Click the Team Status Report icon at the top of the list
3. Click the Zoom button
4. In the Zoomed report window, click File - Save As
5. Select the HTML format for the report
6. Select a folder in which to save the report
7. Give the report an original name and click the Save button

Repeat the above process for each combined Team Status Report. When
finished, launch Word and do the following:

1. Click File - Open
2. Navigate to the folder containing the HTML documents
3. Open the first one
4. Click Insert - File
5. Select another Status Report HTML file and insert it
6. Repeat steps #4-5 and insert each HTML file

Hope this helps.
 
Top