Rolling up resouce costs on summary tasks

B

Brian Bell

Is there any way to have the resouce costs of subtasks roll up to the parent
task when outputing time-phased costs in the "Analyze Timescaled Data in
Excel" function?

Thanks!
 
J

John

Brian Bell said:
Is there any way to have the resouce costs of subtasks roll up to the parent
task when outputing time-phased costs in the "Analyze Timescaled Data in
Excel" function?

Thanks!

Brian,
Not without tweaking the code behind the utility. I have no idea why
Microsoft didn't include that feature in the code. However, why not
simply set up a formula once the data is in Excel? Another option is to
write your own VBA code to do the export. That way you can get whatever
you want.

John
Project MVP
 