S
Scott McClure
This may be a simple Project (rather than server)
question but I'll start here.
We have a group with three subtasks. The tasks have Work
of 16.5 hrs, 36 hrs, and 3 hrs. However, the rollup
header shows Work of 878.7 hrs. I have tried un-denting
(must be a good word for this) the three real tasks and
setting the Work to 0 hrs on the rollup (which is now
normal). When I then re-indent the lower tasks, the
extra hours are added back in. Can anyone give me a clue?
Thanks,
Scott
question but I'll start here.
We have a group with three subtasks. The tasks have Work
of 16.5 hrs, 36 hrs, and 3 hrs. However, the rollup
header shows Work of 878.7 hrs. I have tried un-denting
(must be a good word for this) the three real tasks and
setting the Work to 0 hrs on the rollup (which is now
normal). When I then re-indent the lower tasks, the
extra hours are added back in. Can anyone give me a clue?
Thanks,
Scott