Round up numbers in Usage Grid

H

Hadi

Experts,

is there a way to round up Work and Cost numbers inside the monthly (or
weekly etc) grid when using the Task or Resource Usage Views?

Hadi
 
J

John

Hadi said:
Experts,

is there a way to round up Work and Cost numbers inside the monthly (or
weekly etc) grid when using the Task or Resource Usage Views?

Hadi

Hadi,
In short, "no" and "yes". Work values cannot be rounded but Cost values
can. To round the cost values, go to Tools/Options/View tab and set the
decimal digits to "0".

John
Project MVP
 