Can aanyone let me know how to produce 'S' curve in Project 2002?
P Pat Sep 25, 2003 #2 Richard, Display the Analysis toolbar and you will see "Analyze Timescale Data in Excel". Choose to display Cumulative Cost Curve and complete the wizard. This should give you a graph in Excel of the S curve. Pat