Hey I ahve a problem..maybe someone can point me to a better solution
using ps07/PWA
I have resources which are being used across different projects. Now each
resource rate's change based on the project budgets. However, each time I
MSP07, each time I upload a project and change the std_rate for the resource,
its tells me I am upsetting the Enterprise Pool. But, if I dont change the
Std_rate in each project for the same resource, then the Whole folio is
showing up wrong values.. and this is throwing out the EVM
Early envoirments it was easily progress was tracked against each project on
MSP03 and then aggreated seperately to gather folio values.
any pointers on how to resolve this in an EPM scenerio ?
using ps07/PWA
I have resources which are being used across different projects. Now each
resource rate's change based on the project budgets. However, each time I
MSP07, each time I upload a project and change the std_rate for the resource,
its tells me I am upsetting the Enterprise Pool. But, if I dont change the
Std_rate in each project for the same resource, then the Whole folio is
showing up wrong values.. and this is throwing out the EVM
Early envoirments it was easily progress was tracked against each project on
MSP03 and then aggreated seperately to gather folio values.
any pointers on how to resolve this in an EPM scenerio ?