Same task, multiple places

E

eithen5

Hello,
Im creating a project and I'm noticing that the same task applies to
several areas of the same project. I know that I can simply have
different task list this task as a predecessor but for organization
purposes, it would be nice to see that same task listed several times
under different categories. Is there a way to do this?

Thanks!
 
P

Paul Conroy

Each task in a plan is a unique entity which the exception of cross project
dependancies.

You can have multiple tasks with the same name in a single plan.
 
G

Gary L. Chefetz [MVP]

It sounds as though you aren't structuring your schedules to mirror the
work, rather you're trying to organize your work by department or some other
criteria. If so, you're following a path to confusion and frustration.
Always structure your schedules around the work flow. Use custom attributes
to sort the tasks for others to consume.

--

Gary L. Chefetz, MVP
MSProjectExperts