Same task sequence in PWA than Pro

R

René

Hi,
Is there a way to get the same task listing sequence in
the Task view than in the Project.
I have this user having all his task to the same
resources, and he want that the resources gets the list of
assigned task in the same sequence in the Task view.
From what I have seen, PWA list the task in no specific
ways when no regrouping options is set.

Any ideas?
thanks
 
B

BD

Use the ID column to sort by ID. This should get them in
the same order as the project plan. Each resource would
have to sort their own task sheet because they have the
option of viewing in different orders.
 