Saving baselines for earned value analyses

D

Daniel Sarmento

Hi,

I´ve saved a baseline for my project right before it started.
When I was half way thru the execution I realized that the project was
delayed.
My decision was to cut a task that I´m my opinion wouldn´t compromise the
quality of the project. That way I was able to finish it within my deadline.

After I deleted the task, I wanted to save a new baseline for comparison. No
problems there.

I change the earned value calculation to my new baseline and then I went to
see my new BCWP and BCWS values.

It appers to add the values from my first baseline to the data I had inputed
in my real cost column. My BC value still the same one from my first baseline.

Am I doing something wrong?

Thanks in advance,
Daniel
 
M

Mike Glen

Hi Daniel,

Try posting on the project or server newsgroup as this one is closing down.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 