E
Eddy Recio
Some co-workers and I are experiencing difficulties with
the Resource calendars and predicting the duration, work,
and units.
The main problem is with personnel that work weekends and
either more than the average resource's 8 hours a day,
not to mention if they work only partially on weekends.
For example, we are boggled by unpredictability of the
scheduling. Let say the "project calendar" is 8-5, 8
hours a day, 5 days a week.
If we create a task that is fixed duration and assigned a
resource that works 11 hrs on weekdays (6:30 am -12 pm
and 12:30 - 6:30 pm) and 5.5 (6:30 am -12 pm)on
Saturday, and the task last 4 days and starts on a
Monday. What should this task have for "Work", if
duration is fixed and the resource is set to 100% units?
Please help clarify, we are becoming increasingly
frustrated.
Thanks in advance,
Eddy
the Resource calendars and predicting the duration, work,
and units.
The main problem is with personnel that work weekends and
either more than the average resource's 8 hours a day,
not to mention if they work only partially on weekends.
For example, we are boggled by unpredictability of the
scheduling. Let say the "project calendar" is 8-5, 8
hours a day, 5 days a week.
If we create a task that is fixed duration and assigned a
resource that works 11 hrs on weekdays (6:30 am -12 pm
and 12:30 - 6:30 pm) and 5.5 (6:30 am -12 pm)on
Saturday, and the task last 4 days and starts on a
Monday. What should this task have for "Work", if
duration is fixed and the resource is set to 100% units?
Please help clarify, we are becoming increasingly
frustrated.
Thanks in advance,
Eddy