Can anyone provide some helpful tips in setting up a
schedule performance indicator code in my EGT?
Thanks in advance!
schedule performance indicator code in my EGT?
Thanks in advance!
Dale Howard said:Jason --
You could use a custom enterprise task Duration field for this purpose.
First, rename the field and then enter the formula [Finish Variance] in the
field. Enter your criteria in the graphical indicators section of the
field, along with the stoplight for each criteria. Just a thought. Perhaps
the others will have an idea, too.
Jason said:Dale,
Thanks for the quick reply. I am looking for graphical
(Red, Amber, Green) representation indicating on track,
medium slippage and off track respectively.