S
sumit
Dear All
My client is interested in creating schedule indicators represented by traffic lights (at task and project level) which is fine. The problem is that as the EPM initiative is in its nascent stage no prject manager or team members are updating the project, hence we can't compare schedule from baseline. Can anyone suggest an alternative approach? What I can think of is to compare scheduled finish date from system date, but would this approach be right? Any other tested approach is welcome
Thanks a lot for your help
Regards
Sumit.
My client is interested in creating schedule indicators represented by traffic lights (at task and project level) which is fine. The problem is that as the EPM initiative is in its nascent stage no prject manager or team members are updating the project, hence we can't compare schedule from baseline. Can anyone suggest an alternative approach? What I can think of is to compare scheduled finish date from system date, but would this approach be right? Any other tested approach is welcome
Thanks a lot for your help
Regards
Sumit.