U
UnitZ
Hi,
We have two teams to manage (Malaysia & India). These teams have their
country specific non-working days which have been added on their respective
calendars & attached to the resources. Malaysia holidays are on Standard and
India holidays are on India calendar. The challenge is that MSP2007 schedules
a task (wherein both teams have remote conferences together) on non-working
days falling in either of the calendars. The task cannot be executed if
either of the team is unavailable.
It'd help if MSP doesn't schedule a task at all if the task date is on a
holiday for either of the teams.
I tried looking on the forum if this has been asked before but couldn't find
anything close to the issue. Please help in figuring a way out.
Many thanks!!
We have two teams to manage (Malaysia & India). These teams have their
country specific non-working days which have been added on their respective
calendars & attached to the resources. Malaysia holidays are on Standard and
India holidays are on India calendar. The challenge is that MSP2007 schedules
a task (wherein both teams have remote conferences together) on non-working
days falling in either of the calendars. The task cannot be executed if
either of the team is unavailable.
It'd help if MSP doesn't schedule a task at all if the task date is on a
holiday for either of the teams.
I tried looking on the forum if this has been asked before but couldn't find
anything close to the issue. Please help in figuring a way out.
Many thanks!!