Scheduling Holidays or non-working days

D

Dale Howard [MVP]

Miles --

Do the following:

1. Launch Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Global
3. Click Tools - Change Working Time
4. Enter your 2006 holidays on the appropriate calendar (probably the
Standard calendar)
5. Click OK when finished
6. Save and close the Enterprise Global file

Hope this helps.
 
M

Miles

Thanks! worked perfectly!

Dale Howard said:
Miles --

Do the following:

1. Launch Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Global
3. Click Tools - Change Working Time
4. Enter your 2006 holidays on the appropriate calendar (probably the
Standard calendar)
5. Click OK when finished
6. Save and close the Enterprise Global file

Hope this helps.
 