scheduling overtime hours

W

Weeze

When I schedule overtime hours, Project splits it and assigns a % each day.
How to I schedule overtime for a resource all on one day?
 
J

John

Weeze said:
When I schedule overtime hours, Project splits it and assigns a % each day.
How to I schedule overtime for a resource all on one day?

Weeze,
How did you "schedule" the overtime hours? Project has a couple of
different settings (i.e. working time and Calendar options) than can
effect how extended task hours are handled. You might want to take a
look at our MVP website at: http://www.mvps.org/project/faqs.htm
FAQ 5 - Default Working Hours.

John
Project MVP
 
S

Steve House [Project MVP]

By going into the resource usage sheet and manually entering the overtime on
the day it will occur.
 
W

Weeze

It shows up as overallocation - not overtime - how do I assign overtime pay
to it? Thanks.
 
J

John

Weeze said:
It shows up as overallocation - not overtime - how do I assign overtime pay
to it? Thanks.

Weeze,
I'm not sure if Steve's answer helped but as far as assigning overtime
pay, that is done on the Resource Sheet under the heading of Ovt. Rate.

John
Project MVP
 