H
HT
I would like to assign overtime hours to a resource. Currently this resource
is assigned .5 day (4 hours) to a task. This task's duration is .5 day (4
hours). However, what I really want to do is to assign the entire 4 hours of
this resource assignment to be billed as overtime.
In the Task Form, I have disabled Effort Driven and also set the task type
to fixed duration. I clicked OK after doing so. Yet, when I continue on and
put 4 hours in the Ovt work field of the Task Form, as soon as I click OK the
duration reduces to 0.
If I have stated that I want the duration to remain fixed, why does it then
change? How else can I designate overtime hours for this resource?
is assigned .5 day (4 hours) to a task. This task's duration is .5 day (4
hours). However, what I really want to do is to assign the entire 4 hours of
this resource assignment to be billed as overtime.
In the Task Form, I have disabled Effort Driven and also set the task type
to fixed duration. I clicked OK after doing so. Yet, when I continue on and
put 4 hours in the Ovt work field of the Task Form, as soon as I click OK the
duration reduces to 0.
If I have stated that I want the duration to remain fixed, why does it then
change? How else can I designate overtime hours for this resource?