Scheduling using PWA

N

NewsGroup

Can the Resources make changes to the scheduling of the project by using
PWA?

Regards
Meena.
 
L

Lene

To the best of my knowledge resources cannot reschulede tasks, but they
can add new tasks and they can reject tasks, they can delegate tasks
and they can report their work on a differen date than it was scheduled
for.
 
K

Kevin W Flanagan

Lene is correct, because it requires PM approval before any resource changes
are made to the project schedule. Hlowever, because a resource can adjust
actual hours and add additional hours needed (also must be approved by PM) it
in effect will reschedule the project. Therefore, the PM must be careful
when accepting updates and see the impact before applying them.

Kevin
 
Top