E
Ed T.
Hi;
What I would like to do is to have some way within the Task
Information dialog to cycle through the tasks in the project. In this
particular case, it's to look at the predecessors of all the tasks in
the project.
There are a lot of tasks, and it's tedious to double-click one task,
then click Cancel in the Task Information dialog, then double-click
the next task, etc. Selecting multiple tasks and clicking the Task
Information button does not do this--many things are greyed out in the
Multiple Task Information dialog, including the Predecessors tab.
I tried a few up/down arrows, PageUp/PageDown, but none of those help.
There may well be NO way to do this....too bad!
Thanks for any help.
What I would like to do is to have some way within the Task
Information dialog to cycle through the tasks in the project. In this
particular case, it's to look at the predecessors of all the tasks in
the project.
There are a lot of tasks, and it's tedious to double-click one task,
then click Cancel in the Task Information dialog, then double-click
the next task, etc. Selecting multiple tasks and clicking the Task
Information button does not do this--many things are greyed out in the
Multiple Task Information dialog, including the Predecessors tab.
I tried a few up/down arrows, PageUp/PageDown, but none of those help.
There may well be NO way to do this....too bad!
Thanks for any help.