J
john
I am the PM and am assigning myself to a task. I want to status by using %complete. However, when I go into my timesheet fill out the % on that task, submit it, then approve the task, the project plan opens up but does not status or reflect what I have in my PWA timesheet. Anybody know what I am missing?
Thanks
John
Thanks
John