C
Chris Tomkinson
Hi there! New to the forum, and I'm having some trouble translating my Project 2002 Gantt charts to Project Server 2002 without losing some important data, namely the bar colors. I have changed the bar colors for tasks based upon their status (such as Approved, In Review, Arbitrated, etc). When I import my project to the server, it reverts everything back to the default blue. Upper management loves colors, so I need to display these charts in color in Project Web Access for this to work.
I initially had colored these bars based on a (buggy) VBA script, but I changed that to custom defined bars (under Format->BarStyles menu) using the "Flag1" for "Approved", "Flag 2" for "In Revew", and so on fields but I still can't get Project Server to display those colors.
Does anyone know how to import custom colored Gantt bars to Project Server 2002? It's driving me nuts. Project Server doesn't seem to accept new Gantt bar styles, though it does have some called "Custom Duration" that I have no idea how to use. Thanks in advance!
I initially had colored these bars based on a (buggy) VBA script, but I changed that to custom defined bars (under Format->BarStyles menu) using the "Flag1" for "Approved", "Flag 2" for "In Revew", and so on fields but I still can't get Project Server to display those colors.
Does anyone know how to import custom colored Gantt bars to Project Server 2002? It's driving me nuts. Project Server doesn't seem to accept new Gantt bar styles, though it does have some called "Custom Duration" that I have no idea how to use. Thanks in advance!