Sequencing activities - unwanted red nodes

L

L.C.

I am creating logical relationships and building
dependencies between activities.

Why do the nodes turn red when I want the nodes to remain
blue?

Thank you for your answers!
 
M

Mike Glen

Hi LC,

Welcome to this Microsoft Project newsgroup :)

Red indicates criticality - the underlying foundation on which Project is
built I suggest you read FAQ Item: 42. Guide to Network Analysis.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 