T
trynyti
I have Project Server 2007 setup and all my users (resources) created
with "User can be assigned as a resource" checked and using thier
domain login. I have created a project and created the team from the
enterprise. While in Project 2007 everything appears to be normal, I
can assign tasks to different employees. The problem arises however
when I go to PWA, all the tasks show up in the "My Tasks" list of
whoever publishes the project. I've tested this with another person,
if he checks out the same project, changes the owners, and publishes
the project, then all the tasks show up in his list of "My Tasks",
even though the "Resource Name" column shows the correct owner.
Any ideas on how to correct this?
with "User can be assigned as a resource" checked and using thier
domain login. I have created a project and created the team from the
enterprise. While in Project 2007 everything appears to be normal, I
can assign tasks to different employees. The problem arises however
when I go to PWA, all the tasks show up in the "My Tasks" list of
whoever publishes the project. I've tested this with another person,
if he checks out the same project, changes the owners, and publishes
the project, then all the tasks show up in his list of "My Tasks",
even though the "Resource Name" column shows the correct owner.
Any ideas on how to correct this?