Set Timescale to show period between dates?

V

Veronica

Hi,
I know there are similar questions but I can´t find the exactly one...

I want to show data in Resource Usage View between two exactly set dates.

For example how many hours have I planned on my resources during the 10 th
of February to the 3 rd of March.

Is that possible to have in a view? Can some kind person give me a "step by
step" how to do it? (The best would be to actually se the dates in the
timescale headline too...)

Many Thank´s/Veronica
 
J

Jan De Messemaeker

Hi,

The nearest I can find to your question is to show the "Cumulatibve work"
line (Format, Detail Styles, selectr cumulatibve work, Click Show); the work
betwen two dates is the difference between the cum work on those two dates.

The exact answer can only be found with VBA programming or by exporting the
timescale values to Excel (see the Analysis toolbar)
HTH
 