C
Christophe Dore
Hi,
I am currently evaluating MSProject Standard 2002 ans Project Server 2002.
Let's take an example . I planned a task starting oct 24, ending oct,31
to a developper (name it Dave).
now, for some reasons, Dave starts to work on this task on Oct 27, and
as he is a good developper (or a not-so-much-tester
), he acheives
this task on Oct, 30.
Dave does not have MS PRoject 2002. He uses MSProject Server Web Access.
I have seen how Dave can notify me of the progess of the work, but how
can he tell me when he actually started end finished this task, so that
it changes the fields "Actual Start" and "Actual Finish" of the task in
my MSProject file ?
Is it possible ?
Should I change of release ?
Any idea welcome.
Thanks in advance,
I am currently evaluating MSProject Standard 2002 ans Project Server 2002.
Let's take an example . I planned a task starting oct 24, ending oct,31
to a developper (name it Dave).
now, for some reasons, Dave starts to work on this task on Oct 27, and
as he is a good developper (or a not-so-much-tester
this task on Oct, 30.
Dave does not have MS PRoject 2002. He uses MSProject Server Web Access.
I have seen how Dave can notify me of the progess of the work, but how
can he tell me when he actually started end finished this task, so that
it changes the fields "Actual Start" and "Actual Finish" of the task in
my MSProject file ?
Is it possible ?
Should I change of release ?
Any idea welcome.
Thanks in advance,