Setting base calendar for Enterprise global

N

NewsGroup

I have a base calendar created for my project and I have made it global for
all my projects.
How do I change the calendar in Enterprise Global.

Meena
 
S

Samer Beano

You can achieve that by clicking change working time from tools from project
professional. You can either change the standar calendar or create your own
(by clicking new)

Regards,
 