D
Doug
Project is improperly flagging tasks as changed.
I inherited several projects with actual work recorded and no baseline set.
Opening the project and setting a baseline causes many tasks to be flagged as changed. and displays the "changed Task" indicatior in the left hand column.
Observing 5 or 6 tasks start & finish dates, I see no difference bewteen the dates before baseline and after baseline.
I am not doing anything other that setting a baseline. Why are tasks identified as changed?
I inherited several projects with actual work recorded and no baseline set.
Opening the project and setting a baseline causes many tasks to be flagged as changed. and displays the "changed Task" indicatior in the left hand column.
Observing 5 or 6 tasks start & finish dates, I see no difference bewteen the dates before baseline and after baseline.
I am not doing anything other that setting a baseline. Why are tasks identified as changed?