Hi,
I have a project that I want one of my resources to be able to commit any
available time to (to his assigned tasks). Is there any way when assigning
a resource to a task to have the percentage of time committed to that task
to be the total remaining availability for that resource?
I accidentally had the resource assigned at 100% and then tried leveling and
the undesired result was that it scheduled the task for months into the
future because he was not available at 100% of the time until months down
the road. I would prefer the system to be able to say, he is only available
50% of the time, so that is what we will use.
Is there any way to accomplish something like this?
Thanks,
Richard Millard
I have a project that I want one of my resources to be able to commit any
available time to (to his assigned tasks). Is there any way when assigning
a resource to a task to have the percentage of time committed to that task
to be the total remaining availability for that resource?
I accidentally had the resource assigned at 100% and then tried leveling and
the undesired result was that it scheduled the task for months into the
future because he was not available at 100% of the time until months down
the road. I would prefer the system to be able to say, he is only available
50% of the time, so that is what we will use.
Is there any way to accomplish something like this?
Thanks,
Richard Millard