setting status date time in progress tracking

N

nathanway

can the time of the project status reporting in tracking be set as well as
the date and, if so, how? or can the default time - which seems to be
midnight - be changed to another time of the day?
 
D

Dale Howard [MVP]

nathanway --

When you set the Status date value in the Project Information dialog, the
system normally sets the time to 5:00 PM for that date. If you wish to
change the time, simply click in the Status date field after the date and
manually enter the time. Hope this helps.
 