B
Bill Mc
Our organization has different work weeks for different types of resources.
For example, the project managers and consultants work 8 hr days while the
programmers work 7 hr days. What's the best way to set this scenario up
using Project Server 2007 so that the PM's will be able to assign the proper
calendar for their resoources. Or is the best way to define two base
calendars and then assign them to the resources in Resource Center? Is
there any way for the PM's to manage the "work weeks" in the individual
calendars on their projects. The 'Details' button is deactivated on the
"Change working Time" screen.
Thanks
For example, the project managers and consultants work 8 hr days while the
programmers work 7 hr days. What's the best way to set this scenario up
using Project Server 2007 so that the PM's will be able to assign the proper
calendar for their resoources. Or is the best way to define two base
calendars and then assign them to the resources in Resource Center? Is
there any way for the PM's to manage the "work weeks" in the individual
calendars on their projects. The 'Details' button is deactivated on the
"Change working Time" screen.
Thanks