Setting up Resource leave time in Enterprise resource pool

S

SojAde

Can anyone help, I am trying to setup leave time for some resources. I have
gone through the steps of setting this up within Enterprise Resource pool and
change the dates to non-working time. However whenever I go back to check the
changes don't come through in the PWA or via the Build team Graphs
 
D

Dale Howard [MVP]

SojAde --

I believe you will see the nonworking time updates the next time the OLAP
cube rebuilds. Hope this helps.
 
Top