setting up timesheets in 2003

D

Dave Pliskin, PMP

Help please!!!

I am trying to utilize the timesheet entry within PWA in version 2003. (Not
through Outlook) I can't seem to get the settings so that it will permit time
entry into the actual hours worked. For that matter,, it isn't possible to
change any of the fields on the timesheet view.

I want to use actual hours entered, for a given interval. What should the
settings be?

Thank you in advance for your assistance. I have scanned the previous
entries and did not find an answer to this question.

Thanks.
 
B

Ben Howard

You need to change the tracking method in the admin settings that that it is
set to Hours of work done per period. You'll need to republish the project
to see the details in the timesheet.
 
D

Dave Pliskin, PMP

Ben,

Thanks. That got me closer. However, it only allows a change to hours
remaining, not prompting for hours worked. Perhaps I have the wrong radio
button(s) pushed?

Thanks,

Dave
 