M
martin
I created a project and published to the server. Later I changed the
name and content of it in PP and published again. There was then two
projects of which I deleted the older one. After republishing it only
wants to publish the old version. When I open the project from the
server in PP it is the new one but on the webb access the old one is
the only one.
I created a custom enterprise field with PP. I added a column in PP
in enterprise template to use it. Everytime I start a blank project
it does not have the column and I have to add it manually. When
publishing this project it does not display the contents of this
column (job no) entered in PP in web access. I did add the column in
the web access/admin/customize. It displays the column but empty.
What can I do to have a column to indicate the job physical completion
stage. The %comp closes the task on the timesheet when it reaches
100%. The problem is that if a job takes longer than the schedule and
the timesheet reaches the 100% time mark it ends the task. I tried
both the %comp variants.
Is it possible for the dates and other data to be edited on the
timesheet?
thank you
Martin
name and content of it in PP and published again. There was then two
projects of which I deleted the older one. After republishing it only
wants to publish the old version. When I open the project from the
server in PP it is the new one but on the webb access the old one is
the only one.
I created a custom enterprise field with PP. I added a column in PP
in enterprise template to use it. Everytime I start a blank project
it does not have the column and I have to add it manually. When
publishing this project it does not display the contents of this
column (job no) entered in PP in web access. I did add the column in
the web access/admin/customize. It displays the column but empty.
What can I do to have a column to indicate the job physical completion
stage. The %comp closes the task on the timesheet when it reaches
100%. The problem is that if a job takes longer than the schedule and
the timesheet reaches the 100% time mark it ends the task. I tried
both the %comp variants.
Is it possible for the dates and other data to be edited on the
timesheet?
thank you
Martin