several issues Project 2003

M

martin

I created a project and published to the server. Later I changed the
name and content of it in PP and published again. There was then two
projects of which I deleted the older one. After republishing it only
wants to publish the old version. When I open the project from the
server in PP it is the new one but on the webb access the old one is
the only one.

I created a custom enterprise field with PP. I added a column in PP
in enterprise template to use it. Everytime I start a blank project
it does not have the column and I have to add it manually. When
publishing this project it does not display the contents of this
column (job no) entered in PP in web access. I did add the column in
the web access/admin/customize. It displays the column but empty.

What can I do to have a column to indicate the job physical completion
stage. The %comp closes the task on the timesheet when it reaches
100%. The problem is that if a job takes longer than the schedule and
the timesheet reaches the 100% time mark it ends the task. I tried
both the %comp variants.

Is it possible for the dates and other data to be edited on the
timesheet?

thank you
Martin
 
Top