D
Dominique
Hi,
For a specific task for which the work effort is of 1 day , I have 2
resources allocated, one at 80% (R1) and the other at 40% (R2).
Consequently, the duration of the task is 1.25 days where R1 works 0.5 day on
day 1 and R2 works 0.2 day on day 1, 0.2 day on day 2 and 0.1 day on day 3.
Can you tell what to do to spread the combined effort of R1 and R2 so that
the task is completed is less than a day of elapse time?
R1 + R2 = 120%
1 day of work = 83.33% of a days of R1 + R2 combined.
Thank you,
Dominique.
For a specific task for which the work effort is of 1 day , I have 2
resources allocated, one at 80% (R1) and the other at 40% (R2).
Consequently, the duration of the task is 1.25 days where R1 works 0.5 day on
day 1 and R2 works 0.2 day on day 1, 0.2 day on day 2 and 0.1 day on day 3.
Can you tell what to do to spread the combined effort of R1 and R2 so that
the task is completed is less than a day of elapse time?
R1 + R2 = 120%
1 day of work = 83.33% of a days of R1 + R2 combined.
Thank you,
Dominique.