Sharing Resources late - Gary Dale

S

Shawn

Everyone,
We share resources across the enterprise and lately
resources have been finishing late on other projects which
has caused my projects to start later than originally
scheduled. Can someone give me some advice how to handle
sharing enterprise resources with other pms.

Thank you
Shawn
 
D

Dale Howard

Shawn --

An approach I would recommend for this dilemma is to use the following
procedure:

1. Open each of your own projects that are scheduled to start in the near
future and note the Start date of each project
2. Make a list of your resources that will work on tasks during the first
month or so on each of your near future projects

This list will help you to determine which resources are critical to the
start date and first month of each project. Let's call these resources your
"key resources" for simplicity's sake.

3. In any one of your projects, apply the Resource Usage view
4. Examine each of your "key resources" and determine which other projects
they are assigned to
5. Open each of these other projects as well
6. In the timephased grid, look for overallocations for each of your "key
resources" during the first month of each of your near future projects
7. Use the Work numbers in the timephased grid to determine when each
future project can actually begin with overallocating each of your key
resources
8. Display each of your future projects and save a baseline for each
project (this will show the original planned dates for the project before it
was delayed by resource limitations)
9. In each future project, now set a new Start date for the project
(Project - Project Information), based on your analysis of your key
resources' availability
10. Apply the Tracking Gantt view in each of your future projects, then
show these projects to your boss, pointing out how the resource bottlenecks
in your schedule have delayed your project (the Tracking Gantt view shows
this very nicely)

That's one approach you could use. Because your problems are being caused
by resource availability issues, that is why I recommend a
resource-intensive appoach to solving your problem. Perhaps the others will
have additional thoughts on the subject. Hope this helps.

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
D

David Hunsberger

Shawn -- perhaps you meant your question to be an
organizational/political one. There may be other forums
for management issues of this nature, but I would rely on
your corporate or agency hierarchy to resolve this.
Someone in the organization "owns" the resources that you
need, and that are coming to you late. Someone else high
up in the organization "owns" the project you are working
on, as sponsor or champion or whatever. These people need
to meet and duke it out. As a PM you can prepare for and
facilitate such a meeting, but in my experience a PM can't
command in this situation -- you have to persuade and let
higher powers decide. Formalizing the problem with a
meeting not only helps get a resolution but it also helps
shift responsibility for delays from you to others who are
causing them, and its always nice to shift blame away from
oneself to its rightful owners!

Anyway, I find Dale's approach to be a nice one if you are
talking about the technical side of managing this issue in
Project. All I would add to Dale's answer is that you
might find it convenient to consolidate all the projects
involved into a single mega-project, where all the various
start dates can be seen, filtered, and sorted as
necessary. Also, I sometimes create one or more
milestones in my schedules called "key resources
available" or something similar, showing when I expect to
get my various key resources. My work tasks are linked as
successors to those milestones, as appropriate. Then, in
the Tracking Gantt that Dale recommends, you can clearly
show that slippages are starting with (and due to) the
slippage in such milestones. This brings the resource
problem out of the closet (the hidden resource
availability schedule) into the open on the Gantt Chart.

Regards,
David Hunsberger
Microsoft Project Instructor
www.it7.com
 
Top