Shifting the start date

P

project newby

Hi there,

Does anybody know how to offset a project by a certain period of time
(I want to shift the whole gantt chart by x days).

Thanks
 
J

JulieS

Hi Duncan,

If you want to move all tasks in the project and assuming the tasks are
linked, change the start date of the project in Project > Project
Information.

If you have constraints on the tasks, you will need to use the Adjust
Dates button on the Analysis toolbar.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
P

project newby

Hi Julie,

Thanks for your post, I used excel in the end becasue I do not have an
analysis toolbar and I dont't know how to find it!!.

Thanks
 