Show Baseline 1 bars in Gantt Chart in PWA

G

Greg Jimson

Hi,

how do I configure a view to show the Baseline n values in Project Web
Access?

Thanks
Greg
 
D

Dale Howard [MVP]

Greg --

You can't. Both Project Center and Project Details views show only the
current baseline, as specified in the Baseline set of fields. This is why
the current baseline for your project should also be stored in the Baseline
set of fields. You can use the other 10 sets of Baseline fields to save
alternate baselines, or to back up a baseline after a major change control
procedure. Hope this helps.
 