Project Rookie. How do get the task name to print to the right of the Gantt bar?
J jetfan Mar 6, 2009 #1 Project Rookie. How do get the task name to print to the right of the Gantt bar?
J JulieS Mar 6, 2009 #2 Hi Jetfan, Format > Bar Styles. Select the bar and in the text tab at the bottom, select "Name" from the Right list, replacing Resource Names. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project
Hi Jetfan, Format > Bar Styles. Select the bar and in the text tab at the bottom, select "Name" from the Right list, replacing Resource Names. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project