Showing Project Progress

M

Manish Singh

I need to extract data from Project and show it as a Project Progress graph, how do I do that.
 
M

Mark Durrenberger

Can you describe what you mean by "Project Progress graph" ?

Thanks,
Mark

--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________

The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.

- Sir John Harvey-Jones
Manish Singh said:
I need to extract data from Project and show it as a Project Progress
graph, how do I do that.
 
M

Manish Singh

Well,I need to extract the data from Project and show it as a graph which compares the actual work and the Baselined work for a time duration.

Regards,
Manish
 
D

Dale Howard [MVP]

Manish --

Click View - Toolbars - Analysis. Click the Analyze Timescaled Data in
Excel button on the Analysis toolbar, then export your data to Excel and
graph it the way you desire. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Manish Singh said:
Well,I need to extract the data from Project and show it as a graph which
compares the actual work and the Baselined work for a time duration.
 
M

Manish Singh

Thanks, It did help, I have 2 more queries:
1.Is there any way I can include the milestone information in the graph, and
2.Does MPP provide any report or graph where in I can see the actual % complete against the scheduled baselined % complete
 
D

Dale Howard [MVP]

Manish --

1. Milestones carry no actual work, so I don't see how you could include
milestone information in your graph. Instead, why don't you apply the Gantt
Chart view and apply the Milestones filter?

2. Apply the Gantt Chart view and click Tools - Tracking - Progress Lines.

Hope this helps.




Manish Singh said:
Thanks, It did help, I have 2 more queries:
1.Is there any way I can include the milestone information in the graph, and
2.Does MPP provide any report or graph where in I can see the actual %
complete against the scheduled baselined % complete
 