Showing tasks phase codes in Pro & OLAP

J

jb

All,

I have created an enterprise outline task code for the
DMAIC process. I need to show how much each tak phase is
costing or total work across all projects. I want to show
it in pro & portfolio analyzer.
thx
jb
 
G

Gary L. Chefetz

JB:

Task outline codes do not get published to the cube. You'll need to
customize the cube build process to add this data.

--

Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"