showing the work of different resources depending on their unit

A

asdasdasdasd123

Hi,

when you have just one resource you can see in the column "work" whic
workload this resource has in the specific process.

Is it also possible to see the specific workload of a resource in th
gantt-view, when u have several resources for one process? i already se
their unit in %, but i would like to know what this means in hrs
without to calculate it by hand.

Thx a lot, rgds emeure
 
J

JulieS

Hello emeurer,

Not in the Gantt chart view. However, the task usage view allows you to
see each task and indented underneath each task is the assignment
information for each resource assigned.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 