Jean-Pierre --
To display the WBS field in the task sheet portion of any detailed Project
view in Project Web Access, you will need to ask your Project Server
administrator to do the following:
1. Log into PWA with administrator permissions
2. Click the Admin menu
3. Click the Manage Views link
4. Select any tasks view in the Project section of the data grid (such as
the Tasks Summary view)
5. Click the Modify View button
6. Select the WBS field and copy it to the Displayed fields list
7. Select the WBS field and use the Up or Down button to move it into
position in the table
8. Click the Save Changes button
Steps 4-8 will need to be repeated for each Project view in which you wish
to see the WBS field. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"